“Because an activity’s pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate, the ______ better represents the distribution of possible alternative durations.”

Average Rating
0 out of 5 stars. 0 votes.

“Because an activity’s pessimistic estimate may represent a much greater deviation from the most likely time than its optimistic estimate, the ______ better represents the distribution of possible alternative durations.”

Beta Distribution Estimated time = (optimistic + 4*most likely + pessimistic)/6