Which of the following was developed in the 1950s and uses a statistical approach to estimate the time that will be required to complete project work activities?CPMCCPMPERTPRINCE2©Incorrect. CPM is used for estimating project activity durations and it assumes that the estimates do not vary and time can be reliably estimated.

Average Rating
0 out of 5 stars. 0 votes.

Which of the following was developed in the 1950s and uses a statistical approach to estimate the time that will be required to complete project work activities?CPMCCPMPERTPRINCE2©Incorrect. CPM is used for estimating project activity durations and it assumes that the estimates do not vary and time can be reliably estimated.