“Based on the project expertise and effort required to develop bottom-up estimates, they are normally developed during which phase of a project?PlanningExecutionClosingDefiningIncorrect. The project closing phase is when the project outcomes are delivered to the customer and the customer evaluates them to determine if they are acceptable.”

Average Rating
0 out of 5 stars. 0 votes.

“Based on the project expertise and effort required to develop bottom-up estimates, they are normally developed during which phase of a project?PlanningExecutionClosingDefiningIncorrect. The project closing phase is when the project outcomes are delivered to the customer and the customer evaluates them to determine if they are acceptable.”