“You are well into the final renovations of the restaurant and everything is on schedule and within the budget margins specified in the planning documents. Then a freak snowstorm brings work to a grinding halt for a full week. Because this is always a possibility, you identified this event as a potential risk. Which document should you refer to in order to move the work forward?”

Average Rating
0 out of 5 stars. 0 votes.

“You are well into the final renovations of the restaurant and everything is on schedule and within the budget margins specified in the planning documents. Then a freak snowstorm brings work to a grinding halt for a full week. Because this is always a possibility, you identified this event as a potential risk. Which document should you refer to in order to move the work forward?”

A contingency plan