A project manager wants to know the schedule variance (SV) of a project. Which of the following is the correct formula for determining SV?

Average Rating
0 out of 5 stars. 0 votes.

A project manager wants to know the schedule variance (SV) of a project. Which of the following is the correct formula for determining SV?

SV = EV – PV