(optimistic + pessimistic + (4 * most likely)) / 6 June 20, 2017 mfadmin Project Management Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review. (optimistic + pessimistic + (4 * most likely)) / 6a PERT estimate is calculated using this formula.