____________ in a project schedule identify critical events and other activities that must be performed by specific dates before the project may proceed.Critical pathsMilestonesGantt chartsPert ChartsIncorrect. The critical path is the path of project tasks with the longest duration from the start of the project to its completion.

Average Rating
0 out of 5 stars. 0 votes.

____________ in a project schedule identify critical events and other activities that must be performed by specific dates before the project may proceed.Critical pathsMilestonesGantt chartsPert ChartsIncorrect. The critical path is the path of project tasks with the longest duration from the start of the project to its completion.