“Anita, a project manager, determines that her project team is accomplishing more work at a cost less than anticipated. Which of the following did Anita calculate to determine this good news?”

Average Rating
0 out of 5 stars. 0 votes.

“Anita, a project manager, determines that her project team is accomplishing more work at a cost less than anticipated. Which of the following did Anita calculate to determine this good news?”

CPICorrect. The cost performance index (CPI) uses a ratio that creates a measure of cost efficiency (CPI = EV/AC). CPI values greater than 1 or 100% mean that the project team is completing more work with less cost than expected.