“As you do your initial cost estimates for your various restaurant projects, you should use the bottom-up estimation method.”

Average Rating
0 out of 5 stars. 0 votes.

“As you do your initial cost estimates for your various restaurant projects, you should use the bottom-up estimation method.”

FalseInitial cost estimates should not use the bottom-up method since these estimates are made at the detailed work activity level of the WBS.