“Based on the project expertise and effort required to develop bottom-up estimates, they are normally developed during which phase of a project?PlanningExecutionClosingDefiningIncorrect. The project closing phase is when the project outcomes are delivered to the customer and the customer evaluates them to determine if they are acceptable.”
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.“Based on the project expertise[…]
Read more“During the remodeling of the bar, several tasks are delayed due to the fact that the wall finishes have to be redone after an accidental fire sprinkler discharge. What is this an example of?”
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.“During the remodeling of the[…]
Read moreAestimating method starts at the bottom level of the WBS and aggregate cost estimates up to the total project and they require that people with expertise in doing the work estimate the resources needed to complete each work activity.Incorrect. Parametric estimating methods are top-down estimating methods that are based on the relationship between the current project and historical data.
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.Aestimating method starts at the[…]
Read moreA successor activity cannot start the until the predecessor activity has started in arelationship.Incorrect. The finish-to-start relationship is a logical relationship in which a successor activity cannot start until a predecessor has finished.
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.A successor activity cannot start[…]
Read moreWhat kind of costs are included in the budget to cover unexpected scenarios that may occur?ContingencyDirect costsGeneral and administrative costsManagement reservesIncorrect. A management reserve is an amount added to the overall project budget to cover unknown project risks.
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.What kind of costs are[…]
Read moreYou cannot start the successor activity until the predecessor activity has started in which type of relationship?Finish-to-startStart-to-startStart-to-finishFinish-to-finishIncorrect. The finish-to-start relationship is a logical relationship in which a successor activity cannot start until a predecessor has finished.
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.You cannot start the successor[…]
Read moreYou are nearing the end of the planning phase for your restaurant reconstruction. What will change as you move out of the planning and into the executing phase?
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.You are nearing the end[…]
Read moreTwo examples of parametric estimating are the ratio and apportion methods.
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.Two examples of parametric estimating[…]
Read moreWhich is an example of a product specific deliverable?
Average Rating 0 out of 5 stars. 0 votes.You must log in to submit a review.Which is an example of[…]