Program evaluation and review technique,”(PERT) Calculates the expected value, or weighted average, of critical path tasks to determine project duration by using three estimates: most likely, pessimistic
and optimistic. The PERT calculation is:(optimistic+pessimistic+(4xmost likely))/6″