Schedule performance index,”(SPI) Measures the progress to date against the progress that was planned. The SPI indicator acts as an efficiency rating. If the result is greater than one, performance is better than expected, and you’re ahead of schedule. If it’s less than one, performance is less than expected
and you’re behind schedule. The formula is SPI=EV/PV”