Schedule variance (SV) measures the gap between the earned value (EV) and the planned value (PV). A______________ result indicates that the project is behind based on the baseline schedule.

Average Rating
0 out of 5 stars. 0 votes.

Schedule variance (SV) measures the gap between the earned value (EV) and the planned value (PV). A______________ result indicates that the project is behind based on the baseline schedule.

negative