The schedule variance (SV) compares the value of work completed (EV) with the actual cost (AC) at a given point in time. True or false?
FalseCorrect. The schedule variance (SV) is calculated by subtracting the planned value (PV) from the earned value (EV). The formula is SV = EV − PV.