“Tyrone, a project manager at a computer firm, needs to monitor the schedule of a critical project. What should Tyrone do first?Identify major scope creepAnalyze the completion status of activitiesCalculate all schedule variancesDevelop a schedule baselineIncorrect. A schedule baseline is developed before the project begins and is used for making comparisons when monitoring the schedule.”
…