“Which of the following documents how the various processes and planning areas will be kept in sync throughout the project life cycle?Scope management planIntegration management planProcurement management plan.Risk management planIncorrect. The risk management plan documents how risk events will be identified in advance, monitored, potentially mitigated, and managed across the project life cycle.”
…