“Which of the following is an effective method for monitoring project scope?Revising the schedule frequentlyAnalyzing project varianceGathering performance dataHolding regular status report meetingsIncorrect. When differences between actual performance and the baseline scope are identified, the variance must be analyzed to determine whether a change in scope is warranted. However, analyzing the variance is not a monitoring approach.”
…