Which of the following is based on the baseline schedule and the calendarized baseline budget?Budget at completionPlanned valueActual costEarned valueIncorrect. The budget at completion (BAC) is the approved total baseline budget approved for the completed project.

Average Rating
0 out of 5 stars. 0 votes.

Which of the following is based on the baseline schedule and the calendarized baseline budget?Budget at completionPlanned valueActual costEarned valueIncorrect. The budget at completion (BAC) is the approved total baseline budget approved for the completed project.

Earned Value?