You cannot start the successor activity until the predecessor activity has started in which type of relationship?Finish-to-startStart-to-startStart-to-finishFinish-to-finishIncorrect. The finish-to-start relationship is a logical relationship in which a successor activity cannot start until a predecessor has finished.
…